| Autumn 2007 |
dena accepts a bid of the German company SOLAR23 for the implementation of the solar roofs programme Ndelle, Senegal.
|
| February 2008 |
The components which are necessary for the project are prepared for dispatch in the logisticy centre of SOLAR23 GmbH. The dispatch to Dakar, Senegal takes place in the same month.
|
| March 2008 |
The container arrives in Dakar.
|
| April 2008 |
In the following month the container is transported from Dakar to Ndelle and is stored there until installation.
|
| 19 May 2008 |
The press conference for the beginning of the pilot project takes place in Dakar. On the same day the ground-breaking ceremony takes place in the village Ndelle which is 180 km away.
|
19 May 2008
– 22 May 2008
|
After some preparations the solar system is installed within 4 days.
|
| June 2008 |
The power distribution within the village is installed by the GTZ.
|
| 17 September 2008 |
Inauguration
|
| 24.10.2008 - 25.10.2008 |
Training of 25 technicians and engineers in the offcices of EnergieR in Dakar and on site iin Ndelle.
|
|